Winterstein Modernization Increments 1 and 2

Sacramento, California

Project Description:

 

This project comprised of substantial renovations to the school, completed as Increments #1 and #2. The scope of work included: roofing removal and replacement, abatement, dry-rot repair; new heavy gauge metal gutters and downspouts; fire alarm system upgrades, flooring; HVAC replacement, plumbing; electrical and framing; glazing, plumbing; painting interior and exterior; site preparation, extensive concrete and paving over this 36,673 square-foot campus. 

Project Value: $ 9,580,723

Start date:  6/10/2019

Completion:  2/3/2021
Self-Perform: 38%