PROJECT DESCRIPTION
 
The entire scope of the project included demolition of 48,609 total square feet of roofing over 20 campus buildings followed by single-ply re-roofing and installation of new HVAC units including related:  plumbing, electrical, sheet metal flashing, painting, plastering and custom metal fabrications.  
​
Project Value: $ 1,491,769
Completed: 2018
Self-Perform: 24%

​